Parking, Pipes, Power, Roads and Roofs to be Upgraded
Posted on April 20, 2017
The University’s continuing infrastructure enhancements on the main campus will shift into a higher gear during the upcoming summer semester. Work is scheduled to begin in earnest on May 7, the day after spring commencement exercises. Here is a summary of the activities, with scheduled start and end dates:
- May-Start of Fall Semester: A 248-space, gravel parking lot will be built in the wooded area north of the new Connector Road and east of Health Services Drive. The site will include sidewalks and JagTran access.
- May 7-August 1: Restricted parking at the Student Center, Alumni Hall and Seaman’s Bethel to accommodate installation of underground piping and the reconfiguration of the Student Center loading dock for improved traffic flow and delivery access. The Bookstore entrance will serve as a temporary delivery location.
- May 8-early June: Closure of Cleverdon Parkway for the installation of new turn lanes where Cleverdon meets Old Shell and Hillcrest roads. Detour routes will be provided.
- May 8-August 1: Restricted parking at the Instructional Laboratory Building and Life Sciences Building to accommodate equipment storage for new roofs on those buildings.
- May 8-August 1: Occasional detours just west of the Laidlaw Performing Arts Center for an underground piping project.
- May 8-most of summer: Closure of Tonsmeire Drive to accommodate the construction of an Alabama Power substation north of The Grove.
- Late May to mid-June: Closure of Â鶹´«Ã½ South Drive at the traffic circle for underground piping installation.
- Mid-July to late July: Closure of Stadium Drive at the traffic circle for crosswalk improvements.
- Throughout the summer: Reduced parking in the vicinity of the residence hall under construction next to New Hall and the Jaguar Training Center east of the football practice fields.
Also, several campus roads will receive restriped turning lanes along with crosswalk painting this summer. While all roads should re-open by Aug. 1, scheduled work is subject to change, especially if weather conditions require adjustments to various projects.
For a map showing the affected areas is included on the Facilities Management website.
For specific questions about the projects, please call Facilities Management at 460-7127. Updates on the work will be announced to the University community as needed.
Archive Search
Latest University News
-
Fierce Featherweights
Imagine being able to increase your muscle mass by 40% within a few we...
December 26, 2024 -
South Purchases Traditions Apartment Complex
The Â鶹´«Ã½ expands campus housing with a $20 mill...
December 20, 2024 -
Celebrating 100,000 Graduates
The Â鶹´«Ã½ reaches a milestone at Fall Commenceme...
December 13, 2024 -
Â鶹´«Ã½ Hosts Alabama Numeracy Act Workshop
More than 60 higher education leaders from 35 Alabama institutions uni...
December 11, 2024